Water Intrusion Project (Denali)

PROJECT SCOPE

To reduce occurrences of water intrusion through roofs and windows in the Denali neighborhood, resulting from unintended heat loss and subsequent ice damming.

General Contractor: Davis Constructors & Engineers
Sub Contractor: Rain Proof Roofing

Water Intrusion Project (Denali)

PROJECT SCOPE

To reduce occurrences of water intrusion through roofs and windows in the Denali neighborhood, resulting from unintended heat loss and subsequent ice damming.

General Contractor: Davis Constructors & Engineers
Sub Contractor: Rain Proof Roofing

WHY THIS INFRASTRUCTURE WORK IS IMPORTANT

PRESENT DAY

The Denali neighborhood has seen a substantial uptick in water intrusion work orders over the past two winters (starting in winter of 2022). The water intrusion consistently occurs in similar locations in each home.

AREAS OF CONCERN

The lower roof to wall transitions as well as window drip caps are an entry point for moisture and require repair. Flashing as well as the ice and water shield is not suitable for preventing water intrusion and requires repair.

Shingle repair and full roof replacement is not required; shingles are in good condition.

Pictured above: Flashing and window drip caps along the lower roof will be replaced.
Pictured above: Lower roof flashing, ice and water shield, and transitions will be replaced.

WHAT TO EXPECT

This project will have a moderate impact on your day to day. We’ll do our best to minimize the impact, by providing ample notice via flyer and email.

TIMELINE

Hours: Monday-Friday, 8 AM to 5 PM.

Each building will take approximately 3 business days to complete.

Day 1: Remove siding. Remove shingles.

Day 2: Remove ice and water shield and flashing. Install new step flashing, ice & water shield and shingles

Day 3: Install window drip cap.  Reinstall Siding.

You will receive a flyer approximately 5 days prior to commencement of the job.

EXTERIOR OF HOME

Contractors will be performing work on your roof. For this reason, access to your driveway, back yard, and roof will be required.

Additionally, the contractor will be using hammers and pneumatic nailers, which will result in excess noise.

IN HOME

Entry to homes will not be required during this project.

IN NEIGHBORHOOD

  • Various machinery and equipment will be present in the neighborhood.

SCHEDULE

The projected schedule below is our best estimate as to when work will take place, but is only a projection. We will update this schedule approximately every week. Prior to work commencing on your home, you will receive a flyer with a definitive start date.

COMMUNICATION TIMELINE

We will communicate updates to this project through Door Hangers and Emails. For your convenience, a copy of all of these communications can be found below.

7/3/2024 | Project Overview | Email

7/3/2024 – Completion | Scheduled Flyer | Flyer